No. |
Types of projects |
Specifications of projects |
Principle, procedure, practice |
14 |
Iron or steel industry |
- Iron or steel producer that has a production capacity of 100 tons per day or more |
Submit in the procedure of applying for the projects
|
15 |
Mineral industry that is not an iron or steel industry |
- Mineral producer that has a production capacity of 50 tons per day or more |
Submit in the procedure of applying for the projects |
16 |
Liquor and alcohol production industry
|
-Liquor and alcohol producer that has a production capacity of 40,000 liters per month
-Wine or beer producer that has a production capacity of 600,000 liters per month |
Submit in the procedure of applying for the projects
Submit in the procedure of applying for the projects
|
17 |
Factories that recycle waste products according to the Factory Law |
All capacities
|
Submit in the procedure of applying for the projects |
18 |
Power plants
|
- Power plants that have a production capacity of 10 megawatt per day or more |
Submit in the procedure of applying for the projects |
19 |
Expressways |
All capacities
|
Submit in the procedure of applying for the projects |
20 |
Highway and roads according to the Highway Law that go through the following areas:
20.1 Reserved forest areas
20.2 National parks
20.3 The plain area level 2 according to conclusion of the cabinet
20.4 Mangrove forest
20.5 Fifty meters from beach areas
20.6 Areas 2 kilometers from world heritage sites
20.7 Areas 2 kilometers from ancient remains, antiques, national parks, historical parks and national museums |
All capacities
All capacities
All capacities
All capacities
All capacities
All capacities
All capacities
|
Submit in the procedure of applying for the projects
Submit in the procedure of applying for the projects
Submit in the procedure of applying for the projects
Submit in the procedure of applying for the projects
Submit in the procedure of applying for the projects
Submit in the procedure of applying for the projects
Submit in the procedure of applying for the projects
|
21 |
Public metal transit system |
All capacities
|
Submit in the procedure of applying for the projects |
22 |
Ports |
-Capacity for vessels of 500 gross tons or more
-Quay length of 100 square meters or more
- Total port area is amount of 1,000 square meters or more |
Submit in the procedure of applying for the projects |
23 |
Marinas for docking boats for sport and recreational purposes |
Marinas that have a capacity of 50 vessels or more or an area of 1,000 square meters or more |
Submit in the procedure of applying for the projects
|
24 |
Man-made land projects |
All capacities
|
Submit in the procedure of applying for the projects
|
25 |
Construction or enlargement of buildings close to or in the sea
25.1 Walls close to the beach
25.2 Dams against sand, surfs and water
25.3 Dam against surfs outside the beach |
length of 200 square meters or more
All capacities
All capacities |
Submit in the procedure of applying for the projects
Submit in the procedure of applying for the projects
Submit in the procedure of applying for the projects |
26 |
Air transportation projects
26.1 construction of or enlargement of commercial water airports.
26.2 Water airports |
Runway length of 1,100 meters or more |
Submit in the procedure of applying for the projects |
27 |
Building according to the Building Control Act
27.1 located in an area beside the river, lake, beach or close to or in a national park or historical park
27.2 used for a retail or wholesale business
27.3 used as an office building
|
Buildings that are 23 meters or taller or have all area of 10,000 square meters or more
Buildings that are 23 meters or taller or has a total area of 10,000 square meters or more
Buildings that are 23 meters or taller or have all area in amount of 10,000 square meters or more
|
Submit in the procedure of applying for the projects or the procedure to inform local officers according to Building Control Law
Submit in the procedure of applying for the projects or the procedure to inform local officers according to Building Control Law
Submit in the procedure of applying for the projects or the procedure to inform local officers according to Building Control Law |
28 |
To allot the land for habitation or commerce according to the Land Development Law |
Projects that have more than 500 plot of land or the area more than 100 Rai |
Submit in the procedure of applying for land allotment according to The Land Development Law |
29 |
Hospitals according to the Medical Premises Law
29.1 located in an area close to the river, lake,
beach within 50 meters
29.2 Out of 29.1
|
Hospitals that have 30 or more patients beds
Hospitals that have 60 or more patients beds
|
Submit in the procedure of applying for the projects or the procedure to inform local officers according to Building Control Law
Submit in the procedure of applying for the projects or the procedure to inform local officers according to Building Control Law |
30 |
Hotels according to the Hotel Act |
Hotels that have 80 rooms or more or have a usable area of 4,000 square meters or more |
Submit in the procedure of applying for the projects or the procedure to inform local officers according to Building Control Law |
31 |
Condominiums according to the Building Control Law |
Condominiums that have 80 rooms or more or have a usable area of 4,000 square meters or more |
Submit in the procedure of applying for the projects or the procedure to inform local officers according to Building Control Law |
32 |
Dam Projects
32.1 Capacity
32.2 Area |
100 millions cubic meters or more
15 square kilometers or more |
Submit in the procedure of applying for the projects
Submit in the procedure of applying for the projects |
33 |
Irrigation Projects |
Those that have area of irrigation 80,000 Rai or more |
Submit in the procedure of applying for the projects
|
34 |
All projects that are located in the plain area level 1 according to conclusion of the cabinet |
All capacities
|
Submit in the procedure of applying for the projects
|